DRYDOCKS

Strategic Planning

                                                                                              “The key to successfully
                                                                                            manage drydocks is a risk
                                                                                            analysis to determine the
                                                                                            time factor.”

Jens Kohlmann, vice president of asset management at Carnival Maritime

Drydocks for cruise ships have their          Long-Term                                     actual work that needs to be done, the
own challenges with many variables,                                                         brands define all hotel and hotel-technical
such as the complexity of the projects;          “Long-term strategic planning has been     related tasks.”
lack of capacity at the yards or suppliers;   one of our strengths for a long time,” Kohl-
the weather – as there are no docks with      mann continued. “The partnership between      Varied Workload
roofs; and last, but not least, the logistic  the Costa Group and Chantiers Naval de
efforts due to the worldwide operation of     Marseille supports our goal to plan well in      Drydocks usually involve a variety of
their ships, according to Jens Kohlmann,      advance. In fact, we have drydock plans in    jobs, including propulsion and technical
vice president of asset management, Car-      place for many years to come. It is based     systems overhauls as well as accommo-
nival Maritime in Hamburg.                    on IMO as well as flag state regulations      dations and public space upgrades, Kohl-
                                              and on the planned itineraries of the fleets  mann said.
   “We are going to have five ships in dry-   of AIDA, Costa and Costa Asia.”
dock during the 2018-2019 season,” he                                                          The routine maintenance required by
said. “The Costa Mediterranea, the AIDA-         For each drydock, detailed planning        class usually means hull blasting and coat-
sol and the AIDAcara in Marseille, and the    starts more or less 18 months out, includ-    ing works, and also tasks that would be
Costa Diadema at Fincantieri’s Palermo        ing the budgeting phase.                      disruptive for the passengers if the ship
yard, in addition to the AIDAluna.” (At                                                     was sailing.
press time, Carnival had not yet finalized       Explained Kohlmann: “Our special-
a yard contract for the AIDAluna.)            ized team led by Bernd Bartsch, director         He said technical projects and refur-
                                              major asset management, begins working        bishments may include wastewater treat-
   Four ships are set to follow in the fall:  with the shipyard and suppliers prefer-       ment and ballast water.
the conversion of the Costa neoRiviera        ably between 12 and nine months prior
to the AIDAmira; the Costa Deliziosa,         to define the work to be done, the neces-        There is also maintenance work on
Fascinosa and neoRomantica.                   sary resources and the scope of supplies      shorepower connections and improve-
                                              needed. During this phase, we are also        ments to the ships’ energy efficiencies.
   “The conversion of the Costa neoRiv-       selecting the different contractors. Again,
iera will be our biggest redesign project,”   our long-term planning comes into play as        Other efforts typically focus on up-
Kohlmann added.                               many of the contractors are well-known,       grades and refits in the hotel area, includ-
                                              trusted partners to ensure our high stan-     ing staterooms and restaurants, but also
   “The other ships will go into drydock      dards, and provide predictability for both    IT upgrades.
for technical maintenance as well as vari-    them and ourselves.
ous technical refits and upgrades, replace-                                                    Regular drydock intervals are either 30
ment of certain equipment and enhance-           “The cruise brands are included from       or 60 months, subject to IMO and Italian
ments of the guest experience.”               the very beginning. When it comes to the      State regulations and the age of the ship.

                                                                                               The average drydock ranges from 10
                                                                                            to 14 days.