Costa Statement on Concordia Salvage Operation and Scrapping

At the end of the Conferenza dei Servizi meeting held today in Rome, Costa Crociere reaffirmed its “motivations for the choice of the transportation of the Concordia wreck to Genoa for its dismantling and recycling: Genoa is the only Italian port in which demolition and recycling activities can start immediately and count on the best possible technologies and environmental safety standards.”

“Our company wants to honor a precise commitment: to remove the wreck as soon as possible, in total safety and with the highest environmental standards. To reach this objective, we have turned to the best expertise, the most advanced technological solutions, and unprecedented financial resources. In three weeks we will be ready to tow the Concordia from Giglio Island, in a period of time that statistically presents the most favorable weather and sea conditions. Given this timeframe, the only solution is transporting the wreck into a place which is fully equipped for dismantling with the highest environmental standards.” stated Michael Thamm, Costa Crociere CEO.

“Up to now, all the technical decisions Costa Crociere has made have proven correct –  from the selection and assignment of the removal project to Titan Micoperi, to the parbuckling last September. We believe we deserve the trust of the Italian authorities also for the final phase. The only objective we work for is to close this project in the best possible way”.

“The positive opinion expressed by 17 Ministries and public authorities over 19 that were called to give their technical evaluations today at the Conferenza dei Servizi Servizi, reassures us on the validity of Costa Crociere’s choice for the Genoa project.” addedThamm.

“The Concordia project remains unchanged and is consistent with the one presented in the Conferenza dei Servizi two years ago, that foresaw the towage to an Italian port equipped with dismantling dry docks and facilities. Piombino is not a valid alternative due to the substantial delays in operations to build port infrastructure. We are confident that the Council of Ministers, that is now called to take a final decision, can positively evaluate the solidity of the Genoa project”.

The selection of the project for the demolition and recycling of the wreck presented by the Consortium Saipem/San Giorgio del Porto is the result of the evaluation of all the proposals received by Italian and foreign companies/consortia in the context of the international tender process that was launched in December.  

The choice of this project is the result of technical considerations on the validity of proposed methodology, reliability and expertise of the companies and of the workforce involved, the certainty and rapidity of outcome, the environmental sustainability of all the working phases.

The Concordia wreck removal project is the biggest naval salvage operation in history. Currently more than 350 technicians are working 24/7 to complete sponson installation before the refloating phase. All the 15 starboard sponsons have been installed and now technicians are working on the last 4 sponsons to be positioned on the port side before refloating the wreck and prepare it for towage. The schedule of operations foresees that the refloating can start by the middle of July, with the approval of the Observatory.

Cruise Industry News Email Alerts

Cruise Industry News Email Alerts

 

ABInBev
EMAIL NEWSLETTER

Get the latest breaking cruise newsSign up.

CRUISE SHIP ORDERBOOK

54 Ships | 122,002 Berths | $36 Billion | View

New 2024 Drydock REPORT

Highlights:

  • Mkt. Overview
  • Record Year
  • Refit Schedule
  • 120 Pages
  • PDF Download
  • Order Today
New 2024 Annual Report

Highlights:

  • 2033 Industry Outlook 
  • All Operators
  • Easy to Use
  • Pre-Order Offer
  • Order Today